Implementation Life Cycle Overview

The first step of CallTower’s implementation process is to assign the customer an Implementation Project Manager (IPM). The IPM is responsible for:

  • Establishing clear Microsoft Teams Direct Routing implementation expectations.
  • Ensuring success through execution and delivery.
  • Managing the customer’s experience throughout the process.

Key Steps in the Implementation Process

  1. Assigning the IPM:
    • The IPM creates:
      • Implementation Project Plan
      • Implementation Scope of Work (SOW)
      • Implementation Timeline
    • An introduction email is sent to the customer, followed by scheduling the Kick-Off Call.
  2. Kick-Off Call:
    • Introduces key stakeholders and their roles.
    • Reviews the Implementation SOW, Project Plan, and Timeline.
    • Ensures alignment of customer needs and expectations.
  3. System Setup and Testing:
    • CallTower facilitates the installation and setup of MS Teams Direct Routing, required licencing, and additional features.
    • Builds users, call flows, and other functions in CallTower systems.
    • Conducts early testing and readiness cheques with the customer.
    • Customers complete training segments and readiness work during this phase.
  4. Go Live:
    • Numbers are ported into MS Teams Direct Routing.
    • Post-port Go Live Checklist is completed.
    • Onsite Go Live testing and verification are conducted to ensure full functionality.
  5. Post-Go Live Support:
    • The IPM and the customer’s Main Point of Contact (MPOC) communicate about operations.
    • The MPOC reports issues or challenges, which the IPM addresses with a working plan.
    • Follow-up training and user adoption challenges are tackled.
  6. Acceptance & Project Close Call:
    • The IPM schedules a final call to:
      • Review the implementation process.
      • Transition the account to CallTower’s Service & Support Department.
      • Discuss support processes, resources, and escalation paths.
    • The customer provides feedback and formally accepts the implemented services.

Final Phase: Project Closure

The implementation project is officially closed after the Acceptance & Project Close Call. The account transitions to CallTower’s Service & Support Department for ongoing assistance.